192nd St. Roadway Construction, Center St. to Harrison St., Omaha, NE
192nd Street

192nd St. Roadway Construction, Center St. to Harrison St.

192nd Street

192nd St. Roadway Construction, Center St. to Harrison St.

Client: Douglas County, NE
Project Size: 2.8 miles
Construction Cost: $3.2 million
Project Duration: 4 separate projects spanning over 5 years (1998-2003)

Results: Construction of a 3-lane Portland cement concrete roadway in three separate projects adjacent to nine planned subdivisions plus construction of "F" and "Q" Streets a quarter of a mile east and west. Paving for this project totaled 59,000 square yards.

E&A's Project Scope: Created preliminary through final roadway designs. Completed ownership plans, ROW designs and legal descriptions. Successfully coordinated utilities, residential access, driveway modifications and phasing to allow for simultaneous subdivision construction.

 
 